7 Things to Lock Down Before Your First BIM Coordination Meeting

Most coordination problems don’t start in the model. They start in the first BIM coordination meeting.


You’ve probably been in this one. Half the room is working off last month’s files. Nobody agreed on what counts as a clash, so the first report comes back with 4,000 of them. The mechanical sub can’t commit to a reroute because the person who can say yes isn’t on the call.

The meeting ends with a lot of action items and very little coordination.

We’ve sat in kickoffs on the design side, the GC side, and the trade side. The projects that run smoothly almost always have the same seven things nailed down before the first BIM coordination meeting. Here’s the checklist.

BIM coordination meeting checklist: 7 things to have locked down before your first coordination meeting

The 7-Item BIM Coordination Meeting Checklist

1. The BIM Execution Plan Is Signed Off

Everyone agrees on who models what. The BEP spells out which trade owns which systems, what level of development each model needs to hit, and how the team names and shares files. If it’s still a draft at the first meeting, you’ll spend that meeting arguing about scope instead of coordinating. Need a starting point? Penn State’s BIM Project Execution Planning Guide is a solid template.

2. Shared Coordinates Are Set

One origin point, and every trade on it. This sounds basic, and it is. It’s also the reason a lot of first clash runs are useless. If the plumbing model sits three feet off the structural model, every clash report is noise until somebody fixes it. Autodesk’s shared coordinates workflow for Revit walks through the setup.

3. You Have the Latest Model From Every Trade

Know exactly which version you’re coordinating. Get current models from every trade before the BIM coordination meeting, and agree on who sends updates and how often. Coordinating against an outdated file is just busywork.

4. Clash Rules Are Defined

Agree on what counts before you run a test. Hard clashes, clearance zones, insulation thickness, tolerances. Without rules, a clash test spits out thousands of hits, and the noise buries the real problems. Set the rules once and the reports start meaning something.

5. Zones and Sequence Are Mapped

Coordinate by level or by area, in a set order. Trying to coordinate the whole building at once is how teams stall. Break it into zones, agree on the order, and tie it to the construction schedule. That way you finish coordinating the areas crews will build first before anything else.

6. Decision-Makers Are in the Room

Someone from each trade who can actually say yes. A BIM coordination meeting full of people who have to “check with the office” turns a one-week fix into a three-week fix. Each trade needs someone there who can approve a reroute on the spot.

7. There’s One Issue Tracker

Every clash gets an owner and a due date. Not a spreadsheet on one person’s laptop and a separate list in someone’s email. One shared place where every open issue lives, who owns it, and when it’s due. If an issue doesn’t have an owner, nobody fixes it.

What It Costs to Walk Into a BIM Coordination Meeting Unprepared

The schedule doesn’t wait for coordination to catch up. When the team burns the first few meetings sorting out files, coordinates, and clash rules, the coordination window shrinks. But the pour dates don’t move.

That’s when shortcuts happen. Teams sign off on areas before they’re really coordinated. Crews set sleeves from 2D drawings instead of the model. Then the problems show up in the field, where a reroute means core drilling, rework, and a change order instead of a few clicks in Revit.

You pay back every week you lose up front, with interest. A clean kickoff doesn’t just save a meeting. It protects the whole coordination schedule.

Start Before Problems Reach the Field

None of these seven items is complicated. That’s the point. They’re the basics teams skip when everyone’s in a rush to start running clash tests.

At BIMWERX, this is how we start every project. Our team has worked on the design side, the construction side, and in the trades, so we know what each side needs walking into that first BIM coordination meeting. It’s a big reason 78% of our business comes from repeat clients.

BIMWERX is a BIM/VDC coordination firm that helps GCs, CMs, trade contractors, and design teams build it right in the model before they build it in the field. Have a project kicking off soon? Reach out at info@bimwerx.com or (888) 333-8804.